KEY
DATES |
|
1st stage application prepared and approved by DfES and
DCMS |
Dec 2001 - July
2002
|
|
2nd stage application Outline Business Case (OBC)
prepared |
July 2002 - Feb
2003 |
|
DfES approved allocation of £59.8m |
Feb 2003 |
|
OBC approved by Borough's Cabinet |
March
2003 |
|
OBC formally approved by Government Project Review
Group |
May 2003 |
|
DCMS approved allocation of £10.2m |
July
2003 |
|
Advertised PFI contract and shortlisted 3 bidders to prepare
detailed proposals |
June 2003 - Aug
2003 |
|
Development of Invitation to Negotiate (ITN) documents, detailed
specifications, contract terms and payment mechanism |
Sep 2003 - Feb
2004 |
|
Bidders final ITN proposals returned |
9th Feb
2004 |
|
Formal evaluation of bids completed |
12th July
2004 |
|
Interserve appointed as 'Preferred Bidder' |
26 July
2004 |
|
Final negotiations started with Interserve to agree commercial
terms of PFI contract |
1st Aug
2004 |
|
Detailed planning permission granted for Hadley site |
8th Sept
2004 |
|
Dr Gill Eatough appointed as Principal of the Hadley Learning
Community - Jan 05 start |
23rd Sept
2004 |
|
Enabling works started at Hadley site (fencing, ground
preparation, temporary access, works on existing schools sites -
agreed with Heads) |
11th Nov
2004 |
|
Legal presentation to The Bridge & Temporary Federated
Governing Bodies - explained their roles & responsibilities
within PFI context |
23rd Nov
2004 |
|
Dr Gill Eatough start date as Principal of HLC |
4th Jan
2005 |
|
Detailed planning permission granted for Jigsaw site |
12th Jan
2005 |
|
Staffing protocol agreed with Unions |
Jan 2005 |
|
Legal agreements between LEA & School Governing Bodies
signed |
Feb 2005 |
|
Final Business Case (FBC) submitted to DfES/DCMS |
Feb 2005 |
|
Financial/Commercial close with Interserve / Contract
Awarded |
15th Mar
2005 |
|
Main construction work starts at Hadley |
Mar 2005 |
|
Final approval of credits from DfES and DCMS |
23rd June
2005 |
|
Work commences on Jigsaw site |
18th July
2005 |
|
Appointment of Vice Principals and Assistant Vice
Principals |
May 2005 |
|
Jigsaw Invitation to Negotiate (ITN) submitted to 5 potential
providers of education & care services |
18th July
2005 |
|
Jigsaw bidders final ITN proposals returned |
30th Sept
2005 |
|
Jigsaw evaluation of 5 bids |
Sept 2005 - Nov
2005 |
|
Jigsaw evaluation of top 2 bids |
Nov 2005 - Dec
2005 |
|
Sedgemoor approved as Preferred Bidder to provide education
& care services |
19th Dec
2005 |
|
Appointment of remaining staff continued and finalised at
HLC |
Jan 2005 - June
2006 |
|
Jigsaw contract signed with Sedgemoor |
8th May
2006 |
|
Appointment of Principal for Jigsaw by Sedgemoor |
May 2006 |
|
HLC Secondary School Opening |
4th Sept
2006 |
|
Opening of the HLC primary school, The Bridge school and
community facilities. |
8th Jan
2007 |
|
Opening of Jigsaw |
21st Jan
2007 |
| Grand Opening Event of the HLC by Lord
Grocott of Telford and Andy Hoof - a Mencap trustee and
advocate and former pupil of Birchbank school before it became
the Bridge |
16th March
2007 |