Borough of Telford & Wrekin

HLC - Key Dates

Key Dates

Below is a summary of key dates and events from conception of the project in December 2001 through to opening of the facilities.

KEY DATES

1st stage application prepared and approved by DfES and DCMS

Dec 2001 - July 2002

 

2nd stage application Outline Business Case (OBC) prepared

July 2002 - Feb 2003

DfES approved allocation of £59.8m

Feb 2003

OBC approved by Borough's Cabinet

March 2003

OBC formally approved by Government Project Review Group

May 2003

DCMS approved allocation of £10.2m

July 2003

Advertised PFI contract and shortlisted 3 bidders to prepare detailed proposals

June 2003 - Aug 2003

Development of Invitation to Negotiate (ITN) documents, detailed specifications, contract terms and payment mechanism

Sep 2003 - Feb 2004

Bidders final ITN proposals returned

9th Feb 2004

Formal evaluation of bids completed

12th July 2004

Interserve appointed as 'Preferred Bidder'

26 July 2004

Final negotiations started with Interserve to agree commercial terms of PFI contract

1st Aug 2004

Detailed planning permission granted for Hadley site

8th Sept 2004

Dr Gill Eatough appointed as Principal of the Hadley Learning Community - Jan 05 start

23rd Sept 2004

Enabling works started at Hadley site (fencing, ground preparation, temporary access, works on existing schools sites - agreed with Heads)

11th Nov 2004

Legal presentation to The Bridge & Temporary Federated Governing Bodies - explained their roles & responsibilities within PFI context

23rd Nov 2004

Dr Gill Eatough start date as Principal of HLC

4th Jan 2005

Detailed planning permission granted for Jigsaw site

12th Jan 2005

Staffing protocol agreed with Unions

Jan 2005

Legal agreements between LEA & School Governing Bodies signed

Feb 2005

Final Business Case (FBC) submitted to DfES/DCMS

Feb 2005

Financial/Commercial close with Interserve / Contract Awarded

15th Mar 2005

Main construction work starts at Hadley

Mar 2005

Final approval of credits from DfES and DCMS

23rd June 2005

Work commences on Jigsaw site

18th July 2005

Appointment of Vice Principals and Assistant Vice Principals

May 2005

Jigsaw Invitation to Negotiate (ITN) submitted to 5 potential providers of education & care services

18th July 2005

Jigsaw bidders final ITN proposals returned

30th Sept 2005

Jigsaw evaluation of 5 bids

Sept 2005 - Nov 2005

Jigsaw evaluation of top 2 bids

Nov 2005 - Dec 2005

Sedgemoor approved as Preferred Bidder to provide education & care services

19th Dec 2005

Appointment of remaining staff continued and finalised at HLC

Jan 2005 - June 2006

Jigsaw contract signed with Sedgemoor

8th May 2006

Appointment of Principal for Jigsaw by Sedgemoor

May 2006

HLC Secondary School Opening

4th Sept 2006

Opening of the HLC primary school, The Bridge school and community facilities.

8th Jan 2007

Opening of Jigsaw

21st Jan 2007

Grand Opening Event of the HLC by Lord Grocott of Telford and Andy Hoof - a Mencap trustee and advocate and former pupil of Birchbank school before it became the Bridge
16th March 2007


Get Adobe Reader - link opens in a new window

Please note - Some documents published before 1st December 2006 may contain incorrect contact numbers.
.
For up to date contact numbers please refer to the Guide to Council Services.