Planned highways and transport projects

pride in our community logo

We have 626 miles of road, 743 miles of footpaths, 132 cycle ways, 20,000 street lights, 120 roundabouts, around 400 parks and open spaces and around 15 million trees.

As part of the Council’s 4 year investment programme to Protect, Care and Invest to create a better borough, between 2020 and 2024 we are investing over £50m to keep neighbourhoods safe, clean and well connected. The ‘Pride in Our Community’ programme will deliver improvements to infrastructure including roads, footpaths, parking, sustainable transport, street furniture, drains and structures.

Our highways vision is to ‘Keep Telford Moving’ and in 2021/2022 we will invest £21.6m to deliver over 160 improvement schemes across the borough.

The 12-month programme includes road safety schemes, the creation of more residential parking spaces in local neighbourhoods, road improvements, footpath improvements, drainage works as well as work on highways structures such as bridges.

The latest findings by the Department for Transport show that the condition of our roads are better than the regional and national averages, which is quite an achievement given the current financial challenges we face.

This £21.6m investment will be invested as follows:

  • £7.635m into roads and footpaths
  • £1.2m into Structures
  • £1.15m into drainage and council owned assets
  • £0.671m into street furniture, lighting and lines
  • £2.583m into sustainable transport, parking and safety schemes
  • £8.355m into major projects.

These improvements will be delivered in partnership with the Council's new highways contractor Balfour Beatty Living Places.

In addition to planned works, we also carry out reactive maintenance to keep the travelling public safe. We are working with Balfour Beatty to look after our roads, footpaths and infrastructure, visit our YouTube channel to watch the 'keeping Telford and Wrekin Moving' video to find out interesting facts and figures.

Visit our report it section to report highway faults and issues online


Overview of the schemes happening over the next 12 months in each ward

Please note: planned delivery dates are shown, however these dates are subject to change due to a number of factors such as weather, coordination with utilities and unforeseen ground conditions.

This table provides an overview of the improvement schemes happening in Admaston and Bratton over the next 12 months.
Type of works  Location Planned delivery date

Surface Treatments

Donnerville Gardens June 2021
Surface Treatments Shawbirch Road (Service Road) September 2021

This table provides an overview of the improvement schemes happening in Apley Castle over the next 12 months.
Type of works   Location Planned delivery date
Road Restraint Upgrade (RRS) A442 (adjacent Hoo Farm Roundabout) To be confirmed

This table provides an overview of the improvement schemes happening in Arleston over the next 12 months.
Type of works  Location Planned delivery date
Preventative Arleston Avenue June 2021
Resurface Bayley Road Phase 2 June 2021
Resurface Highway View September 2021
Resurface Princess Avenue (Side Road) September 2021

This table provides an overview of the improvement schemes happening in Brookside over the next 12 months.
Type of works  Location Planned delivery date
Resurfacing/Surface Treatment All of Brookside Summer 2021
Major works A442 (Brockton Lopp) To be confirmed

This table provides an overview of the improvement schemes happening in Church Aston and Lilleshall over the next 12 months
Type of works  Location Planned delivery date
Traffic Calming Church Aston and Lilleshall August 2021
Drainage Pinewoods June 2021
Drainage The Spinney August 2021

This table provides an overview of the improvement schemes happening in College over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Fairfield Court September 2021
Resurfacing Beacon and Market Street Both Sides Autumn 2021
Surface Treatment Victoria Avenue and Railway Station May 2021
Network Improvements Bennetts Bank January 2022

This table provides an overview of the improvement schemes happening in Dawley and Aqueduct over the next 12 months.
Type of works  Location Planned delivery date
Resurface Webb Crescent Complete
Resurface Manor Road Complete
Resurface Heath Hill Roundabout June 2021
Surface Treatment Aqueduct Road August 2021
Surface Treatment Bridgnorth Road September 2021
Surface Treatment Cooke Drive May 2021
Surface Treatment Beames Close May 2021
Surface Treatment Ivatt Close May 2021
Surface Treatment Morton Court May 2021
Residential Parking Improvements Pageant Drive To be confirmed
Traffic Calming Old Office Road and Concorde August 2021

This table provides an overview of the improvement schemes happening in Donnington over the next 12 months.
Type of works  Location Planned delivery date
Resurface Wrekin Drive - Cul De Sac September 2021
Resurface Hawthorn Road August 2021
Surface Treatment Ewart Road September 2021
Surface Treatment Ash Road June 2021
Surface Treatment Farm Lane Bungalows August 2021
Traffic Calming Donnington September/October 2021
Residential Parking Improvements Celadine Way To be confirmed
Drainage Winifreds Drive November 2021

 
Type of works Location Planned delivery date
Junction Improvement  A41 between Chetwynd Fairs and Stamford Bridge and Chester Road Junction August 2021
Essential Maintenance A442 Waters Upton Bridge July 2021
Drainage Newport Road September 2021
Drainage Tibberton September 2021
Drainage Bolas Bridge to Bolas September 2021

This table provides an overview of the improvement schemes happening in Ercall over the next 12 months.
Type of works  Location Planned delivery date
Traffic Calming Holyhead Road and Ercall Lane October-November 2021
Traffic Calming Haygate Road Near Bowring Park November 2021

This table provides an overview of the improvement schemes happening in Hadley and Leegomery over the next 12 months.
Type of works  Location Planned delivery date
Preventative Gladstone Street June 2021
Preventative Grovefields June 2021
Preventative Manor Road September 2021
Preventative Hurleybrook Way August 2021
Drainage Crescent Road August 2021

This table provides an overview of the improvement schemes happening in Haygate over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments Alexandra Road Completed
Surface Treatments Rose Crescent Completed
Residential Parking Improvements Simon Close To be confirmed

This table provides an overview of the improvement schemes happening in Horsehay and Lightmoor over the next 12 months.
Type of works  Location Planned delivery date
Resurface Lawley Common Roundabout June 2021
Surface Treatments Old Office Road October 2021
Traffic Calming Woodhouse Lane and Frame Lane January 2022

This table provides an overview of the improvement schemes happening in Ironbridge Gorge over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments Jiggers Bank To be confirmed
Patching Darby Road Complete
Traffic Calming Jiggers Bank Depending on structural works
Essential Maintenance Jiggers Bank July 2021
Essential Maintenance Belle Vue October 2021
Essential Maintenance Madeley Road February 2022
Drainage Coalport High Street October 2021

This table provides an overview of the improvement schemes happening in Ketley and Overdale over the next 12 months.
Type of works  Location Planned delivery date
Resurface    
Surface Treatments Red Lees September 2021
Surface Treatments Marlborough Way - Estate June 2021
Surface Treatments Park Lane June 2021
Surface Treatments The Crest June 2021
Surface Treatments Old Coppice Grange June 2021
Surface Treatments The Rock May 2021
Surface Treatments Mannerley Lane June 2021
Surface Treatments Hartley Close June 2021
Surface Treatments Laurel Lane Cul De Sac September 2021
Surface Treatments Mount Side June 2021
Surface Treatments Ivy House Paddocks Estate - Including Low Valley Close June 2021
Surface Treatments Garfield Road May 2021
Networks Improvement Colliers Way October 
Traffic Claming Lawley Drive To be confirmed
Residential Parking Improvements Princes End Drive Near 61 To be confirmed
Essential Maintenance Hollinswood Interchange  no 2 Railway Bridge August-September 2021
Essential Maintenance Hollinswood Interchange no 4 Railway Bridge August-September 2021
Major Works Hollinswood Interchange To be Confirmed
Major Works - replacement and repair upgarades A442 Hollinswood to Castlefields To be confirmed
Major Works - Signs and lines A442 Hollinswood to Castlefields To be confirmed
Drainage Holyhead Road July 2021
Drainage Riddings Close July 2021
Drainage Shepherds Lane August 2021

This table provides an overview of the improvement schemes happening in Madeley and Sutton Hill over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments High Street May 2021
Surface Treatments Southfield June 2021
Resurfacing/Surface Treatments All of Sutton Hill Autumn 2021
Residential Parking Improvement Sutton Way To be confirmed

This table provides an overview of the improvement schemes happening in Madeley and Sutton Hill over the next 12 months.
Type of works  Location Planned delivery date
Resurface Powis Place September 2021
Surface Treatments Princes Charles Crescent June 2021
Surface Treatments Dovedale Fold May 2021
Surface Treatments Dawley Bank July-August 2021
Surface Treatments Dark Lane September 2021
Surface Treatments Alma Avenue September 2021
Residential Parking Improvements Melbourne Close, Dawley To be confirmed

This table provides an overview of the improvement schemes happening in Muxton over the next 12 months.
Type of works  Location Planned delivery date
Resurface New Trench Road - A518 August 2021
Surface Treatments Columbine Way June 2021

This table provides an overview of the improvement schemes happening in Newport North and West over the next 12 months.
Type of works  Location Planned delivery date
Resurface Heathwood Road September 2021
Resurface Greenacres Way September 2021
Surface Treatments Broomfield Road/Broomfield Place September 2021

This table provides an overview of the improvement schemes happening in Newport South and East over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Tudor Close August 2021
Surface Treatment Harcourt Drive September 2021
Drainage Maynards Croft June 2021
Dainage Water Lane August 2021

This table provides an overview of the improvement schemes happening in Oakengates and Ketley Bank over the next 12 months.
Type of works  Location Planned delivery date
Resurface Lincoln Road Area August 2021
Resurface Vicar Street August 2021
Resurface Charlton Street August 2021
Resurface Church Street August 2021
Resurface The Woodlands September 2021
Surface Treatments Hawthorne Close September 2021
Surface Treatments Station Approach September 2021
Residential Parking Improvements First Avenue To be confirmed
Drainage New Road June 2021
Drainage Trench Lock June 2021

This table provides an overview of the improvement schemes happening in Park over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Admaston Road August 2021

This table provides an overview of the improvement schemes happening in Shawbirch over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Span Meadow June 2021
Surface Treatment Oakfield Road June 2021

This table provides an overview of the improvement schemes happening in St Georges over the next 12 months.
Type of works  Location Planned delivery date
Preventative West Street June 2021
Surface Treatment Hollybirch Grove/Dorran Place Completed

This table provides an overview of the improvement schemes happening in The Nedge over the next 12 months.
Type of works  Location Planned delivery date
Resurface Dallamoor, Hollinswood July 2021
Preventative Dalelands, Hollinswood July 2021
Preventative Dunsheath May 2021
Preventative Deepdale July 2021
Resurface A5 Telford Way Complete
Resurface Stafford Park 18 July 2021
Resurface Randlay Interchange North Bound Off Slip Complete
Patching Hollinswood Interchange To be completed through EPMIP scheme
Residential Parking Improvements Daywell To be confirmed
Major Works Randlay Interchange To be confirmed
Major Works Stirchley Interchange To be confirmed

This table provides an overview of the improvement schemes happening in Wrockwardine  over the next 12 months.
Type of works  Location Planned delivery date
Pedestian Signing Improvements The Wrekin August 2021
Traffic Calming Little Wenlock October- November 2021
Drainage Castlecroft to Suningdal Junction October 2021
Drainage Rodington October 2021
Drainage Charlton November 2021

This table provides an overview of the improvement schemes happening in Wrockwardine Wood and Trench over the next 12 months.
Type of works  Location Planned delivery date
Structural Patching A442 Trench Lock to Wombridge Interhchange Complete
Surface Treatment Tudor Meadow June 2021
Surface Treatment Wrockwardine Wood Way August 2021
Patching Gibbons Road S278 works to be completed by developer
Traffic Calming Trench Road and Wombridge Road October 2021
Residential Parking Improvements Johnstone Close To be confirmed
Drainage Trench Road July 2021
Drainage Richmond Avenue November 2021

Last updated: 25/06/2021 12:26