Planned highways and transport projects

pride in our community logo

We have 626 miles of road, 743 miles of footpaths, 132 cycle ways, 20,000 street lights, 120 roundabouts, around 400 parks and open spaces and around 15 million trees.

As part of the Council’s 4 year investment programme to Protect, Care and Invest to create a better borough, between 2020 and 2024 we are investing over £50m to keep neighbourhoods safe, clean and well connected. The ‘Pride in Our Community’ programme will deliver improvements to infrastructure including roads, footpaths, parking, sustainable transport, street furniture, drains and structures.

Our highways vision is to ‘Keep Telford Moving’ and in 2021/2022 we will invest £21.6m to deliver over 160 improvement schemes across the borough.

The 12-month programme includes road safety schemes, the creation of more residential parking spaces in local neighbourhoods, road improvements, footpath improvements, drainage works as well as work on highways structures such as bridges.

The latest findings by the Department for Transport show that the condition of our roads are better than the regional and national averages, which is quite an achievement given the current financial challenges we face.

This £21.6m investment will be invested as follows:

  • £7.635m into roads and footpaths
  • £1.2m into Structures
  • £1.15m into drainage and council owned assets
  • £0.671m into street furniture, lighting and lines
  • £2.583m into sustainable transport, parking and safety schemes
  • £8.355m into major projects.

These improvements will be delivered in partnership with the Council's new highways contractor Balfour Beatty Living Places.

In addition to planned works, we also carry out reactive maintenance to keep the travelling public safe. We are working with Balfour Beatty to look after our roads, footpaths and infrastructure, visit our YouTube channel to watch the 'keeping Telford and Wrekin Moving' video to find out interesting facts and figures.

Visit our report it section to report highway faults and issues online


Overview of the schemes happening over the next 12 months in each ward

Please note: planned delivery dates are shown, however these dates are subject to change due to a number of factors such as weather, coordination with utilities and unforeseen ground conditions.

This table provides an overview of the improvement schemes happening in Admaston and Bratton over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments Donnerville Gardens Completed
Surface Treatments Shawbirch Road (Service Road) Completed

This table provides an overview of the improvement schemes happening in Apley Castle over the next 12 months.
Type of works   Location Planned delivery date
Road Restraint Upgrade (RRS) A442 (adjacent Hoo Farm Roundabout) To be confirmed

This table provides an overview of the improvement schemes happening in Arleston over the next 12 months.
Type of works  Location Planned delivery date
Preventative Arleston Avenue Completed
Resurface Bayley Road Phase 2 Completed
Resurface Highway View Completed
Resurface Princess Avenue (Side Road) Completed

This table provides an overview of the improvement schemes happening in Brookside over the next 12 months.
Type of works  Location Planned delivery date
Resurfacing/Surface Treatment All of Brookside Completed
Major works A442 (Brockton Lopp) Spring 2022

This table provides an overview of the improvement schemes happening in Church Aston and Lilleshall over the next 12 months
Type of works  Location Planned delivery date
Traffic Calming Church Aston and Lilleshall August 2021
Drainage Pinewoods Completed
Drainage The Spinney October 2021

This table provides an overview of the improvement schemes happening in College over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Fairfield Court Completed
Resurfacing Beacon and Market Street Both Sides Deferred 2022/23
Surface Treatment Victoria Avenue and Railway Station Completed
Network Improvements Bennetts Bank January 2022

This table provides an overview of the improvement schemes happening in Dawley and Aqueduct over the next 12 months.
Type of works  Location Planned delivery date
Resurface Webb Crescent Completed
Resurface Manor Road Completed
Resurface Heath Hill Roundabout Completed
Surface Treatment Aqueduct Road Completed
Surface Treatment Bridgnorth Road Completed
Surface Treatment Cooke Drive Completed
Surface Treatment Beames Close Completed
Surface Treatment Ivatt Close Completed
Surface Treatment Morton Court Completed
Residential Parking Improvements Pageant Drive Completed
Traffic Calming Old Office Road and Concorde August 2021

This table provides an overview of the improvement schemes happening in Donnington over the next 12 months.
Type of works  Location Planned delivery date
Resurface Wrekin Drive - Cul De Sac Completed
Resurface Hawthorn Road Completed
Surface Treatment Ewart Road Completed
Surface Treatment Ash Road Completed
Surface Treatment Farm Lane Bungalows Completed
Traffic Calming Donnington November 2021
Residential Parking Improvements Celadine Way Spring 2022
Drainage Winifreds Drive March 2022

 
Type of works Location Planned delivery date
Junction Improvement  A41 between Chetwynd Fairs and Stamford Bridge and Chester Road Junction August 2021
Essential Maintenance A442 Waters Upton Bridge October 2022
Drainage Newport Road Completed
Drainage Tibberton Spring 2022
Drainage Bolas Bridge to Bolas November 2021

This table provides an overview of the improvement schemes happening in Ercall over the next 12 months.
Type of works  Location Planned delivery date
Traffic Calming Holyhead Road and Ercall Lane October-November 2021
Traffic Calming Haygate Road Near Bowring Park December 2021

This table provides an overview of the improvement schemes happening in Hadley and Leegomery over the next 12 months.
Type of works  Location Planned delivery date
Preventative Gladstone Street Completed
Preventative Grovefields Completed
Preventative Manor Road Completed
Preventative Hurleybrook Way Completed
Drainage Crescent Road Completed

This table provides an overview of the improvement schemes happening in Haygate over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments Alexandra Road Completed
Surface Treatments Rose Crescent Completed
Residential Parking Improvements Simon Close 2022

This table provides an overview of the improvement schemes happening in Horsehay and Lightmoor over the next 12 months.
Type of works  Location Planned delivery date
Resurface Lawley Common Roundabout Completed
Surface Treatments Old Office Road Completed
Traffic Calming Woodhouse Lane and Frame Lane January 2022

This table provides an overview of the improvement schemes happening in Ironbridge Gorge over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments Jiggers Bank Completed
Patching Darby Road Completed
Traffic Calming Jiggers Bank Depending on structural works
Essential Maintenance Jiggers Bank July 2021
Essential Maintenance Belle Vue January 2022
Essential Maintenance Madeley Road January 2022
Drainage Coalport High Street Spring 2022

This table provides an overview of the improvement schemes happening in Ketley and Overdale over the next 12 months.
Type of works  Location Planned delivery date
Resurface    
Surface Treatments Red Lees Completed
Surface Treatments Marlborough Way - Estate Completed
Surface Treatments Park Lane Completed
Surface Treatments The Crest Completed
Surface Treatments Old Coppice Grange Completed
Surface Treatments The Rock Completed
Surface Treatments Mannerley Lane Completed
Surface Treatments Hartley Close Completed
Surface Treatments Laurel Lane Cul De Sac Completed
Surface Treatments Mount Side Completed
Surface Treatments Ivy House Paddocks Estate - Including Low Valley Close Completed
Surface Treatments Garfield Road Completed
Networks Improvement Colliers Way December 2021
Traffic Claming Lawley Drive To be confirmed
Residential Parking Improvements Princes End Drive Near 61 Completed
Essential Maintenance Hollinswood Interchange  no 2 Railway Bridge March 2022
Essential Maintenance Hollinswood Interchange no 4 Railway Bridge March 2022
Major Works Hollinswood Interchange October 2021
Major Works - replacement and repair upgarades A442 Hollinswood to Castlefields To be confirmed
Major Works - Signs and lines A442 Hollinswood to Castlefields To be confirmed
Drainage Holyhead Road November 2021
Drainage Riddings Close

Phase 1 Completed

Phase 2  Spring 2022

Drainage Shepherds Lane October 2021

This table provides an overview of the improvement schemes happening in Madeley and Sutton Hill over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatments High Street Completed
Surface Treatments Southfield Completed
Resurfacing/Surface Treatments All of Sutton Hill Works ongoing
Residential Parking Improvement Sutton Way 2022

This table provides an overview of the improvement schemes happening in Madeley and Sutton Hill over the next 12 months.
Type of works  Location Planned delivery date
Resurface Powis Place Completed
Surface Treatments Princes Charles Crescent Completed
Surface Treatments Dovedale Fold Completed
Surface Treatments Dawley Bank Completed
Surface Treatments Dark Lane Completed
Surface Treatments Alma Avenue Completed
Residential Parking Improvements Melbourne Close, Dawley 2022

This table provides an overview of the improvement schemes happening in Muxton over the next 12 months.
Type of works  Location Planned delivery date
Resurface New Trench Road - A518 Completed
Surface Treatments Columbine Way Completed

This table provides an overview of the improvement schemes happening in Newport North and West over the next 12 months.
Type of works  Location Planned delivery date
Resurface Heathwood Road Completed
Resurface Greenacres Way Completed
Surface Treatments Broomfield Road/Broomfield Place Completed

This table provides an overview of the improvement schemes happening in Newport South and East over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Tudor Close Completed
Surface Treatment Harcourt Drive Completed
Drainage Maynards Croft Completed
Dainage Water Lane August 2021

This table provides an overview of the improvement schemes happening in Oakengates and Ketley Bank over the next 12 months.
Type of works  Location Planned delivery date
Resurface Lincoln Road Area Completed
Resurface Vicar Street Completed
Resurface Charlton Street Completed
Resurface Church Street Completed
Resurface The Woodlands Completed
Surface Treatments Hawthorne Close September 2021
Surface Treatments Station Approach 2022/23
Residential Parking Improvements First Avenue 2023
Drainage New Road Phase 2 to be confirmed
Drainage Trench Lock Completed

This table provides an overview of the improvement schemes happening in Park over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Admaston Road Completed

This table provides an overview of the improvement schemes happening in Shawbirch over the next 12 months.
Type of works  Location Planned delivery date
Surface Treatment Span Meadow Completed
Surface Treatment Oakfield Road Completed

This table provides an overview of the improvement schemes happening in St Georges over the next 12 months.
Type of works  Location Planned delivery date
Preventative West Street Completed
Surface Treatment Hollybirch Grove/Dorran Place Completed

This table provides an overview of the improvement schemes happening in The Nedge over the next 12 months.
Type of works  Location Planned delivery date
Resurface Dallamoor, Hollinswood Completed
Preventative Dalelands, Hollinswood Completed
Preventative Dunsheath Completed
Preventative Deepdale Completed
Resurface A5 Telford Way Completed
Resurface Stafford Park 18 Completed
Resurface Randlay Interchange North Bound Off Slip Completed
Patching Hollinswood Interchange 2022/23
Residential Parking Improvements Daywell 2024
Major Works Randlay Interchange Spring 2022
Major Works Stirchley Interchange November 2021

This table provides an overview of the improvement schemes happening in Wrockwardine  over the next 12 months.
Type of works  Location Planned delivery date
Pedestian Signing Improvements The Wrekin August 2021
Traffic Calming Little Wenlock October- November 2021
Drainage Castlecroft to Suningdal Junction Completed
Drainage Rodington Completed
Drainage Charlton November 2021

This table provides an overview of the improvement schemes happening in Wrockwardine Wood and Trench over the next 12 months.
Type of works  Location Planned delivery date
Structural Patching A442 Trench Lock to Wombridge Interhchange Completed
Surface Treatment Tudor Meadow Completed
Surface Treatment Wrockwardine Wood Way Completed
Patching Gibbons Road 2022/23
Traffic Calming Trench Road and Wombridge Road October 2021
Residential Parking Improvements Johnstone Close 2022
Drainage Trench Road Completed
Drainage Richmond Avenue January 2022

Last updated: 31/03/2022 12:04