A41 Resurfacing Forton Roundabout to Buttermilk
A41 Resurfacing Scheme
As part of the Council’s ongoing investment into its roads and footpaths, we will shortly be carrying out the final phase of works on the A41, from Forton Roundabout to Buttermilk Hill (Telford and Wrekin’s Northern Boundary with Shropshire). These works will include carriageway resurfacing along with ironwork reinstatements and replacement lining and road studs along this section.
The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. The project is being delivered by Telford & Wrekin Council's principal contractor Balfour Beatty with associated sub-contractors.
Works Programme
The programme of works will be conducted from 4 August - 15 August 2025.
Please note: that the operations are weather dependant and the days and timings when the A41 is closed during this period may change. Signage on site will be provided to communicate up to date information.
Phase 4 – Resurfacing Scheme
- Monday 4 August 2025 – Friday 15 August 2025.
- Road closure will be in place week days only from 7am - 4pm.
- Week 1 –
- Removal and replacement of road surface (8,500m2).
- Week 2 –
- Replacement of road markings and road studs
- Ironworks reinstatements.
- Gully cleansing.
Traffic Management
Extents
The A41 will be closed between the Telford/Shropshire Boundary and Forton Roundabout with a diversion route via the A53, the A442 and the A518.
Access
The works are being delivered by Telford and Wrekin Councils Highways team along with Balfour Beatty Living Places and specialist sub-contractors. The team will endeavour to work closely with the community and specifically residents and businesses situated within the closure extents to allow access to properties throughout the project, but there may be times where the diversion route will need to be followed. We are unable to provide access through the site during closure periods for safety reasons.
The A41 will be closed in sections between Forton Roundabout and the Standford Bridge Junction during the periods detailed above. Access will be maintained across the A41 in two locations throughout all closure periods.
Communications
Signage
Warning signs will be installed along the A41 from Monday 21 July 2025 along with an advanced warning email issued to stakeholders and a letter will be delivered to properties in the local area.
Variable message signs will be installed on site during the construction period to provide live updates on closure dates throughout the period.
Last updated : 22 July 2025