A41 Resurfacing Scheme

As part of the Council’s ongoing investment into its roads and footpaths, we will shortly be carrying out works on the A41, from Forton Roundabout to Buttermilk Hill (Telford and Wrekin’s Northern Boundary with Shropshire). These works will include carriageway patching, resurfacing and surface dressing along with ironwork reinstatements and replacement lining and road studs along this section. 

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. The project is being delivered by Telford & Wrekin Council's principal contractor Balfour Beatty with associated sub-contractors.

Works Programme

The programme of works will be conducted in four phases between May and August 2025.

Phasing

Carriageway resurfacing works are planned along the A41 from Sambrook to Forton Roundabout. The works will be

Phase 1 - Preparatory Works

  • Monday 19 May – Thursday 22 May.
  • Road closure at night between 7pm - 5am.
  • Carriageway patching, ironwork replacements and removal of lining and road studs .

Phase 2 - Surface Treatment

  • Wednesday 28 May – Friday 30 May.
  • Road Closure in the day between 7am - 4pm.
  • Surface Dressing treatment. This is broken down into two operations. The first application will be conducted on Tuesday and Wednesday, with the second application on Friday and Saturday.

Phase 3 - Lining and Road Studs

  • Monday 2 June – Thursday 5 June
  • Road Closure in the day between 7am -4pm.
  • Lining and Reflective Road Studs

Please note: that the operations in Phase 2 and Phase 3 are weather dependant and the days and timings when the A41 is closed during this period may change. Signage on site will be provided to communicate up to date information.

Phase 4 – Resurfacing Scheme

  • Monday 4 August – Friday 15 August.
  • Road Closure will be in place 24/7.
  • Lining and Road Stud replacements.

Closure Times

Where possible works have been planned to reduce disruption with short duration closures and/or night shifts:

  • Phase 1 – Short duration night closures - A41 reopened in the day and for the weekend
  • Phase 2 – Short duration day closures - A41 reopened in the afternoon
  • Phase 3 – Short duration day closures - A41 reopened in the afternoon and weekend
  • Phase 4 – Road closured for duration of this phase.

Traffic Management

Extents

The A41 will be closed between the Telford/Shropshire Boundary and Forton Roundabout with a diversion route via the A53, the A442 and the A518.

Access

The works are being delivered by Telford and Wrekin Councils Highways team along with Balfour Beatty Living Places and specialist sub-contractors. The team will endeavour to work closely with the community and specifically residents and businesses situated within the closure extents to allow access to properties throughout the project, but there may be times where the diversion route will need to be followed. We are unable to provide access through the site during closure periods for safety reasons.

The A41 will be closed in sections between Forton Roundabout and the Standford Bridge Junction during the periods detailed above. Access will be maintained across the A41 in two locations throughout all closure periods.

Communications

Signage

Warning signs will be installed along the A41 from Monday 12 May along with an advanced warning email issued to stakeholders and a letter will be delivered to properties in the local area.

Variable message signs will be installed on site during the construction period to provide live updates on closure dates throughout the period.