During the period 6 July 2020 – 27 July 2020 routine environmental maintenance operations will be carried out across the dual carriageway network. In order to maintain social distancing on site, the activities that will be carried out will be limited to ‘essential’ work only.
The majority of works will be undertaken under full closures, these closures will take place overnight to minimise disruption and the impact on the road network.
A variety of essential maintenance works will be undertaken under these closures as follows:
- gully emptying
- grass cutting
- street light testing
- minor carriageway repairs
- litter picking
- hedge cutting
- tree felling
- vehicle barrier repairs
- a variety of highway asset surveys.
The programme and diversion routes for this scheme can also be viewed and downloaded below. Please note that this may be subject to change dependant on adverse weather conditions and other unforeseen circumstances out of our control, as well as the developing situation with COVID-19. If the programme is updated, this will be published on the web site as a revision.
- Trench Lock Interchange – Wombridge Interchange
Closure: 6 July 2020 - 7pm - 7am
- Wombridge Interchange - Hollinswood Interchange
Closure: 7 July 2020 and 8 July 2020 - 7pm – 7am
- Hollinswood Interchange – Randlay Interchange
Closure: 9 July 2020 - 7pm – 7am
- Randlay Interchange – Stirchley Interchange
Closure: 13 July 2020 - 7pm – 7am
- Stirchley Interchange to Brockton Loop
Closure: 14 July 2020 - 7pm – 7am
- Brockton Loop to Brockton Roundabout
Closure: 15 July 2020 - 7pm – 7am
- Stirchley Interchange lane 1 and 2
Lane closure: 21 July 2020 - 7pm – 6am
- Randlay Interchange lane 1 and 2
Lane closure: 21 July 2020 - 7pm – 6am -
Trench Lock Interchange - Inside Lane Only
Lane closure: 21 July 2020 - 12am - 5am - Wombridge Interchange lane 1 and 2
Lane closure: 22 July 2020 - 7pm – 6am
- Hollinswood Interchange lane 1 and 2
Lane closure: 22 July 2020 - 7pm – 6am
- Hollinsgate - Lanes 2 only
Lane closure: 22 July 2020 - 7pm - 7am
- Brockton Roundabout to Sutton Hill Roundabout - lanes 2 only
Lane closure: 23 July 2020 - 7pm - 7am
- Castle Farm Interchange to Naird Roundabout
Closure: 20 July 2020 - 7.40pm – 7am - Naird to Randlay Interchange
Closure: 21 July 2020 - 7pm – 7am
- Brockton Loop to Castlefields Roundabout
Closure: 16 July 2020 - 7pm – 7am
- Kemberton Road - lanes 2 only
Lane closure: 23 July 2020 - 7pm - 7am
- Telford Way: Hollinswood Interchange to Priorslee Roundabout
Closure: 12 July 2020 - 10am - 4pm
- Rampart Way - Lanes 2
Lane closure: 27 July 2020 - 7pm - 7am
- Ketley Brook Interchange – Ketley Dingle Interchange
Closure: 12 July 2020 - 4am – 10am
- Lawley Drive - M54 junction 6 to Lawley Common Roundabout
Closure: 19 July 2020 - 8am – 8pm
- Beveley Roundabout to Mossey Green Roundabout
Closure: 22 July 2020 - 7pm – 7am
- West Centre Way - Lawley traffic lights to Old Park Roundabout
Closure: 26 July 2020 - 8am – 8pm
- Hall Park Way - Forge Roundabout to Hall Roundabout - lanes 2 only
Closure: 27 July 2020 - 7pm – 7am
Last updated: 20/05/2020 16:17