Resurfacing Schemes

As part of the Council’s 4 year investment programme to ‘Protect, Care and Invest to create a better borough’. Between 2020 and 2024 over £50m is being invested to keep neighbourhoods safe, clean and well connected. The ‘Pride in our Community’ Highways Capital Programme will deliver improvements to infrastructure including roads, footpaths, parking, sustainable transport, street furniture, drains and structures.

Our highways vision is to ‘Keep Telford Moving’ and in 2021/2022 we will invest £21.6m to deliver over 160 improvement schemes across the borough.

Road Maintenance: Surface Treatment Schemes

A programme of Surface Treatment is due to commence on various sites (see Resident Letter for a list of sites with forecasted dates) on 10 May 2021 between the hours of 7.30am and 6pm. The works are a two stage process requiring two applications. This means that Contractors and Traffic Management will visit each site twice, please refer to the Resident Letter for programme dates. The work is, however, weather dependant and the programme dates shown may be subject to change:

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Surface Dressing (RMS) and lining (WJ UK).

Detailed Works Programme

  • The works will be managed under Stop and Go / Convoy working. This means that access through sites will be mostly maintained, apart from short periods where the material must harden.
  • Residents and businesses directly affected will receive an information leaflet and resident letter 24/48 hours prior to contractors arriving on site. 
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing.

Surface Treatment Scheme 

We are planning to carry out Surface Treatments to improve the condition of the highway.

Provisional start and end dates

  • Start date 2 June 2021.
  • End date: 18 June 2021.

Proposed Traffic Management Arrangements

Traffic will be managed by using Stop and Go / Convoy working. 

Proposed Working Hours

Road Maintenance: A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) Resurfacing Scheme

A programme of resurfacing is due to commence on A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) on 4 May 2021 and be completed by 12 May (Weekdays only 8am - 6pm). The work is, however, weather dependant and the programme dates shown may be subject to change:

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), Loop Installation (Dynniq) and lining (WJ UK).

Detailed Works Programme

  • Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption. 
  • Site specific designs and diversion routes can be found below.
  • Where closures are in force, a diversion will be signed on site. 
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing. 

A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) Resurfacing Scheme

We are planning to carry out resurfacing A5 Telford Way (Hollinswood Roundabout to Priorslee Roundabout) to improve the condition of the highway.

Provisional dates

  • Start date 4 May 2021.
  • End date: 12 May 2021.

Proposed Traffic Management Arrangements

Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works

Proposed Working Hours

Road Maintenance: A442 Trench Lock Interchange to Wombridge Interchange Southbound Resurfacing Scheme

A programme of resurfacing is due to commence on A442 Trench Lock Interchange to Wombridge Interchange Southbound on 26 April 2021 and be completed by 5 May 2021 (Weekdays only 8am - 6pm and excluding the Bank Holiday). The work is, however, weather dependant and the programme dates shown may be subject to change:

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum), and lining (WJ UK).

Detailed Works Programme

  • Road closures will be used at the site with appropriate diversion signage as this allows for works to be completed quickly, safely and efficiently and to minimise disruption. 
  • Site specific designs and diversion routes can be found below.
  • Where closures are in force, a diversion will be signed on site. 
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing. 

A442 Trench Lock Interchange to Wombridge Interchange Southbound Resurfacing Scheme

We are planning to carry out Resurfacing Scheme on A442 Trench Lock Interchange to Wombridge Interchange Southbound to improve the condition of the highway.

Provisional Dates

  • Start date 26 April 2021.
  • End date: 5 May 2021.

Traffic Management will be removed over the weekend and Bank Holiday. 

Proposed Traffic Management Arrangements

Traffic will be managed by using a road closure and diversion (for further details please see resident letter / diversion plan attached), which will be clearly signed throughout the works

Proposed Working Hours

Last updated: 25/05/2021 10:36