Resurfacing Schemes

As part of the Council’s 4 year investment programme to ‘Protect, Care and Invest to create a better borough’. Between 2020 and 2024 we are investing over £50m to keep neighbourhoods safe, clean and well connected. The ‘Pride in our Community’ Highways Capital Programme will deliver improvements to infrastructure including roads, footpaths, parking, sustainable transport, street furniture, drains and structures.

Our vision is to ‘Keep Telford Moving’ and in 20/21 we will invest £22m to deliver 200 improvement schemes across the borough. These improvements will be achieved in partnership with the Council’s Principal Contractor Balfour Beatty.

Prior to works commencing, detailed project information will be accessible below. Major schemes include:

  • Beverley Roundabout
  • Hollinswood Interchange (Slip Road)
  • B5053 - Shawbirch to Longon on Tern
  • A442 - Brockton Loops
  • A442 - Randlay to Stirchley Northbound
  • Vineyard Road
  • Boughey Road
  • A442 - Crudgington
  • Queen Street - Madeley

Road Maintenance: Beverley Roundabout and Approaches Resurfacing Scheme

A programme of Resurfacing Beverley Roundabout, it’s approaches and a large section on the B5061 Holyhead Road past the Travis Perkins entrance are due to begin on 1 September 2020 for 2 weeks (Monday to Friday 7pm - 6am). The work is, however, weather dependant and the programme dates shown may be subject to change:

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).

Detailed Works Programme

  • Road closures will be used at most sites with a combination of temporary traffic signals as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
  • Access for residents / business users, including the Shell Garage will be maintained throughout the works; however road closures to through traffic will be in place for most sites. Any traffic management used will be in place for the duration of the scheme dates to facilitate the works.
  • Site specific designs, diversion routes and phasing plans can be found below.
  • Where closures are in force, a diversion will be signed on site.
  • All properties with frontages onto the site or where a cul de sac is within the site will receive a letter from Telford and Wrekin Council.

Advanced information signs will be placed on each site 2 weeks prior to works commencing.

Beverley Roundabout and approaches - Resurfacing Scheme

We are planning to carry out full resurfacing of roundabout along with extensive drainage cleansing at the above location to improve the condition of the highway.

Provisional Dates

  • Start date: 1 September 2020
  • End date: 11 September 2020

Proposed Traffic Management Arrangements

Roundabout Resurfacing

Traffic will be managed by using a road closure on different phases of the roundabout (for further details please see resident letter / phasing plan attached) with a full diversion in place around each phase of the works with all other traffic being managed with temporary traffic signals. The roundabout will be fully open traffic each morning by 6am.

Proposed Working Hours

Picture of A442 brockton loops resurfacing scheme

Road Maintenance: A442 Brockton Loops Resurfacing Scheme

A programme of Resurfacing A442 Brockton Loops, is due to begin on 14 September 2020 A closure of the A4169 (Northbound only 7pm – 6am) from Castlefields Roundabout (See Below).

Diversions will be clearly signed and symbolised. The work is, however, weather dependant and the programme dates shown may be subject to change.

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).

Detailed Works Programme

  • Road closures will be used at most sites with a combination of temporary traffic signals as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
  • Any traffic management used will be in place for the duration of the scheme dates to facilitate the works.
  • Site specific designs, diversion routes and phasing plans can be found below 
  • Where closures are in force, a diversion will be signed on site.
  • All properties with frontages onto the site or where a cul de sac is within the site will receive a letter from Telford and Wrekin council
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing.

A442 Brockton Loops

We are planning to carry out full resurfacing of both Northbound and Southbound at the above location to improve the condition of the highway.

Provisional Dates

  • Start Date: 14 September 2020
  • End Date: 18 September 2020 Roundabout. Diversions will be clearly signed and symbolised.

Proposed Traffic Management Arrangements

Resurfacing

The works will be carried out under a 24 hour road closure of the Brockton Loops and Brockton Way Northbound, there will be a night time closure of the A4169 (Northbound only 7pm – 6am) from Castlefields.

Proposed Working Hours

Road Maintenance: A442 Lane 1 adjacent to Randlay Interchange resurfacing, drainage repairs and kerb replacements

Image of A442 lane 1 adjacent to randlay interchange resurfacing drainage repairs and kerb replacements

A programme of resurfacing, drainage repairs and kerb replacements on A442 Lane 1 adjacent to Randlay Interchange, is due to begin on 12 October 2020 for 2 weeks. The works will be carried out under a 24 hour road closure with a short diversion up onto Randlay Interchange and back down the on-slip at Randlay interchange, re-joining the A442 carriageway.

The work is, however, weather dependant and the programme dates shown may be subject to change.

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork and drainage repairs (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).

Detailed Works Programme

  • Any traffic management used will be in place for the duration of the scheme dates to facilitate the works.
  • Site specific designs, diversion routes and phasing plans can be found below 
  • Where closures are in force, a diversion will be signed on site.
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing

A442 Lane 1 adjacent to Randlay Interchange

We are planning to carry out full resurfacing of Lane 1 at the above location to improve the condition of the highway.

Provisional Dates

  • Start Date: 12 October 2020
  • End Date: 23 October 2020

Proposed Traffic Management Arrangements

The works will be carried out under a 24 hour road closure with a short diversion up onto Randlay Interchange and back down the on-slip at Randlay interchange, re-joining the A442 carriageway.

Proposed Working Hours

Road Maintenance: A442 Hollinswood Northbound Off-slip Reconstruction, resurfacing and kerb replacements schemeImage of A442 hollinswood northbound off slip reconstruction resurfacing and kerb replacements scheme

A programme of reconstruction, resurfacing and a new kerbline A442 Hollinswood Northbound Off-slip, is due to begin on 21 September 2020 for 3 weeks. The works will be carried out under a 24 hour road closure of the off-slip, a 24 hour lane 1 closure of the A442 adjacent to the off-slip and a 24 hour lane 1 closure adjacent to the off-slip on Hollinswood Interchange.

The diversion will be clearly signed. The work is, however, weather dependant and the programme dates shown may be subject to change.

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork, reconstruction and drainage (G & N Groundworks), Kerbing (Extrudakerb), Signal boxes (Dynniq), DynoRod (Drainage CCTV), Traffic Management (Quantum) and lining (WJ UK).

Detailed Works Programme

  • Any traffic management used will be in place for the duration of the scheme dates to facilitate the works.
  • Site specific designs, diversion routes and phasing plans can be found below 
  • Where closures are in force, a diversion will be signed on site.
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing.

A442 Hollinswood Northbound Off-slip

We are planning to carry out full resurfacing and partial reconstruction of the Hollinswood Northbound off-slip at the above location to improve the condition of the highway.

Provisional Dates

  • Start Date: 21 September 2020
  • End Date: 9 October 2020

Proposed Traffic Management Arrangements

The works will be carried out under a 24 hour road closure of the off-slip, a 24 hour lane 1 closure of the A442 adjacent to the off-slip and a 24 hour lane 1 closure adjacent to the off-slip on Hollinswood Interchange. The diversion will be clearly signed.

Proposed Working Hours

Road Maintenance: A442 Crudgington to Waters Upton Structural Patching Scheme

A programme of Structural Patching and joint sealing is due to commence between Sleep Farm, Crudgington and River Lane, Waters Upton on 30 November 2020 for 2 weeks (Monday to Friday 7pm - 6am). The work is, however, weather dependant and the programme dates shown may be subject to change:

The funding for the work has come from the Council’s highway capital programme as part of its ‘Pride in Our Community’ programme to make the borough a better place to live, work and visit. 

The Project is being delivered by our principal contractor Balfour Beatty with sub-contractors for Resurfacing (Tarmac), Ironwork (G & N Groundworks), Traffic Management (Quantum) and lining (WJ UK).

Detailed Works Programme

  • Road closures will be used at most sites with a combination of temporary traffic signals as this allows for works to be completed quickly, safely and efficiently and to minimise disruption.
  • Access for residents / business users, will be maintained throughout the works; however road closures to through traffic will be in place for most sites. Any traffic management used will be in place for the duration of the scheme dates to facilitate the works, Residents may be required to drive to the opposite end of the closure for access.
  • Site specific designs, diversion routes and phasing plans can be found below.
  • Where closures are in force, a diversion will be signed on site.
  • All properties with frontages onto the site or where a cul de sac is within the site will receive a letter from Telford & Wrekin Council.
  • Advanced information signs will be placed on each site 2 weeks prior to works commencing.

Proposed working hours and plans

Last updated: 20/11/2020 15:07