A442 Southbound
Monday 5 July 2021 to Wednesday 7 July 2021:
- lane 1 closure Greyhound to Hollinswood Interchange and full closure of Hollinswood southbound off slip
- download the diversion plan to Randlay Interchange for southbound traffic.
Wednesday 7 July 2021 to Thursday 8 July 2021:
- full closure of Hollinswood southbound on slip
- download the diversion plan to Greyhound Interchange for southbound traffic.
Friday 9 July 2021 to Wednesday 14 July 2021:
- lane 1 closure Hollinswood Interchange to Randlay Interchange.
A442 Northbound
Sunday 4 July 2021 7pm to 7am Monday 5 July 2021:
- full closure for placement of temporary vehicle containment barriers
- download the diversion plan A via Madeley and Halesfield back to Stirchley Interchange
- download the diversion plan B via Madeley and Halesfield back to Stirchley Interchange.
Monday 5 July 2021 to Thursday 8 July 2021:
- lane 1 closure Brookside Interchange to Stirchley Interchange.
Thursday 8 July 2021 to Friday 9 July 2021:
- full closure of Stirchley northbound off slip
- download the diversion plan to Randlay Interchange for Northbound traffic.
Please note: the programme is provided as a guide and for reference purpose only. The dates may vary nominally for operational reasons and in case of inclement weather.